The Journey of Crafting Lakeside Residences
From the first stone to the final touch, every phase reflects our commitment to design excellence and refined living.
-
Groundwork & Foundation (Feb – Apr 2025)
Site cleared, soil stabilized, and foundation works completed, setting a solid base for villas and apartment structures.
-
Structural Framework (May – Jul 2025)
Main structures for villas and apartments erected; beams, slabs, and walls completed across most blocks.
-
Finishing & Interior Works (Aug – Nov 2025)
Ongoing tiling, plastering, plumbing, and electrical installations — focus on interior finishes and quality detailing.
-
Landscaping & Final Touches (Dec 2025 – Mar 2026)
External works, gardens, and shared amenities (pool & parking) nearing completion, preparing for handover at 70 % progress.